Skip to content
Join our Newsletter

Exploded Prince George mill closes – possibly for good

The Lakeland Mills planer in Prince George, site of a fatal explosion in April, closed down indefinitely yesterday, leaving workers out of a job once again.
gv_20120822_biv0105_120829978
Todd Wikjord/CBC

The Lakeland Mills planer in Prince George, site of a fatal explosion in April, closed down indefinitely yesterday, leaving workers out of a job once again.

The CBC reported this morning that the last of the remaining inventory wood was put through the planer on Tuesday.

The Lakeland Mills explosion in April killed two men, injured 24 others and destroyed the sawmill, but the planer was able to reopen in May, allowing 22 employees to return to work.

The company is waiting on information from its insurance company and WorksafeBC before deciding whether or not to rebuild, according to Greg Stewart, president of Sinclair Group Forest Products, the company that owns the majority of the mill.

Stewart said there's a solid case to be made for rebuilding the mill.

"I think we have some of the best employees in the industry. We have a fibre situation which is different from a lot of mills in the north. We have local owners that are very supportive of the community that have shown their commitment and stood by us through this tragedy."

CBC reported that the company will continue to provide fibre for the city of Prince George's district energy system and the University of Northern BC's bio-energy plant.

A report released Tuesday noted that safety reports from as early as 2008 cited dust as a potential hazard at the mill. WorksafeBC is currently investigating what caused the explosion.